Rea Vaya construction & traffic update: 5 - 11 Feb
- Details
- 05 February 2016
Rea Vaya Phase 1C continues with construction of the new Grayston Drive Pedestrian and Cycling Bridge over M1 Highway and construction of cycling lane and sidewalk from Katherine Street in Sandton to as far as Andries Street in Wynberg along Grayston Drive.
Check out this week's road closures/traffic diversions for the following areas
Grayston off-ramp Southbound
Erection of formwork, fixing reinforcing steel and pouring of concrete to the Pier 6 Pier head next to the Grayston off-ramp Southbound.
Construction of footings for the support work at span 8 next to the Grayston Drive off-ramp Southbound.
M1 Highway on-ramp Northbound
Erection of formwork, fixing reinforcing steel and pouring of concrete to the Pier 3 and 4 Pier heads next to M1 Highway on-ramp Northbound.
Installation of Working Anchors at the North West and South West Anchor Blocks next to the M1 Highway on-ramp Northbound
Draining of water from the Pylon excavation adjacent to the M1 Highway Northbound carriageway.
Construction work - further info
Click here for details of the upcoming week's construction work, along with photos of last week's work.
- New Grayston Drive Pedestrian Bridge over M1 Highway: Katherine Street to Andries Street (Section 15 I) - view weekly update
- Katherine Street: Corner West Street to the Corner Marlboro Drive (Section 8A and 8B ) -view weekly update